Measure D - Series C
Project Planned expenditures
Project Planned expenditures
PGUSD issues Series C of the 4 part Measure D in 2024. Thhis Series authorized PGUSD $8.75 million for projects assoctaied with Measure D, Series C Reprioritization List.
Generally, Series C Projects include:
Generally, Series C Projects include:
- HVAC Mechanical upgrades as sites
-
- Districtwide focus on energy efficiency projects such as building envelope modifications, lighting (interior and exterior retrofit to LED), stadium lighting retrofit, plumbing and sewer projects.
- Building Envelopes
- Playground updates with adaptive equiptment
- Playground blacktop areas sealing, stripping and ADA
Summer 2025 Projects Include:
Robert H. Down Elementary School
- Removal of modular building
- Chair Lift Repairs in Ottertorium
- Roof Coating - Main Building and A-Wing
- Replacement of Kinder play structure and Swings (to include adaptive equiptment)
- Stage curtain replacement
- BASRP flooring and modernization of 2nd half
Forest Grove Elementary School
- Replacement of Kinder play structure and Swings (to include adaptive equiptment)
- Flooring in Room F2
Pacific Grove High School
- Gas Leak Detection Survey
- Gym Electrical
- Water leak repair
- Campus electrical switchgear upgrade
Pacific Grove Middle School
- Roof coating & gutter replacement Bldg A&B
- Playground structure repairs
- Otis Elevator repairs, service and testing
David Avenue School Campus - Exterior painting and dry rot removal
- Gutters
- Restroom Modernization
- General landscaping
All Sites will have tree removal and/or safety pruning
2025-2026 Project Plan of Priorities - TBD